Freestone County power projects

Freestone County, Texas has 22 active power projects totalling 5,357 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 2,265 MW (42%). The largest single project is Jewett Energy Center 1 Gas (1,274 MW natural gas). 8 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
22
5.4 GW capacity
IA signed or later
8
36% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Freestone County

COD change
10/01/2026
Silver Dollar Solar · Solar · Freestone County
Projected COD moved 04/28/2028 → 10/31/2029. Delay #1 for this project.
+18 mo
COD change
10/01/2026
Bar Candela Solar SLF · Solar · Freestone County
Projected COD moved 12/31/2027 → 05/16/2029. Delay #1 for this project.
+17 mo
COD change
10/01/2026
Silver Dollar Storage · BESS · Freestone County
Projected COD moved 04/28/2028 → 10/31/2029. Delay #1 for this project.
+18 mo
COD change
10/01/2026
Bar Candela Storage SLF · BESS · Freestone County
Projected COD moved 12/31/2027 → 05/16/2029. Delay #1 for this project.
+17 mo

All projects

ProjectFuelMWSubstationStageCOD
Jewett Energy Center 1 GasGas1,274Tap #3391 JEWETT_N5 - #46020 LMEST_POI_5 and Tap #3390 JEWETT_S5 - #46020 LMEST_POI_5IA Signed11/01/2029
BM Freestone Energy CenterGas991Loop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Brown W to Tarantulla Ckt 1 (PTI#3381-3344) at 31.813367° -96.147730°FIS Requested09/20/2029
Silver Dollar SolarSolar302Tap 345 kV Big Brown 3380 to Navarro 68091 ckt#2FIS Requested10/31/2029
Amerada SolarSolar302Tap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5FIS Requested12/30/2028
Simsboro StorageBESS302Tap Outlaw (3386) – Limestone (46020)FIS Requested03/31/2029
Piedra SolarSolar282Tap 345-kV line Navarro (68091) – Limestone (46020))Sync Approved01/15/2027
Utley SolarSolar222Tap 345kV 3381 Big Brown Switch - 3391 JewettIA Signed05/11/2028
Douie SolarSolar221Tap 138 kV 3501 Sea way Teague - 3394 JewettIA Signed04/18/2028
Freestone Battery Storage ProjectBESS2103134 RICHLAND CHAMBERS 345kV (PSS/E Bus Name: RICHLND1_5)FIS Requested12/16/2028
Avant Prairie BESSBESS202Tap 345kV BIGBRNE (#3380) - JEWETT (#3390) CKT 1FIS Approved04/16/2029
Bar Candela Solar SLFSolar200Long Lake Sub (Bus 3280) – Long Lake Tap Switch (Bus 3279)IA Signed05/16/2029
Silver Dollar StorageBESS153Tap 345 kV Big Brown 3380 to Navarro 68091 ckt#2FIS Requested10/31/2029
Amerada StorageBESS151Tap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5FIS Requested07/21/2028
Turtle Rock StorageBESS136Tap 138 kV 13501 Clayhill to 13681 ReedFIS Requested07/02/2028
Fairway StorageBESS120Tap 138kV 3503 FAIRWPOD_8 - 196 FAIRFIELDIA Signed09/24/2027
Piedra BESSBESS104Tap 345-kV line Navarro (68091) – Limestone (46020))IA Signed12/01/2027
Timber Cove Solar SLFSolar100Tap 138 kV 212 Winkler - 3510 Pin OakFIS Requested06/01/2027
Ratcliff SolarSolar86Tap 138kV 3279 Long Lake Tap Switch - 3280 Long LakeFIS Requested04/07/2029
Bar Candela Storage SLFBESS0Long Lake Sub (Bus 3280) – Long Lake Tap Switch (Bus 3279)IA Signed05/16/2029
Timber Cove Storage SLFBESS0Tap 138 kV 212 Winkler - 3510 Pin OakFIS Requested06/01/2027
Three Canes Gas P1Gas0#3344 Tarantula Switching StationFIS Requested11/30/2027
Three Canes Gas P2Gas0Tap on the 345 kV Outlaw Switch (bus #3386) to Limestone Plant Station (bus #46020) Transmission LineFIS Requested11/30/2027

For residents and landowners

What power projects are planned in Freestone County?
ERCOT's October 2026 report lists 22 active projects in Freestone County totalling 5,357 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.