29INR0298 · Gas · Freestone County
BM Freestone Energy Center
BM Freestone Energy Center is a 991 MW natural gas project in Freestone County, Texas, connecting at Loop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Brown W to Tarantulla Ckt 1 (PTI#3381-3344) at 31.813367° -96.147730°. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/20/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0298
- Capacity
- 991 MW
- Fuel
- Gas (CC)
- County
- Freestone County
- Interconnecting entity
- Black Mountain Energy Storage II
- Projected COD
- 09/20/2029
- Entered queue
- 02/11/2026
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/11/2026Entered the queue with 991 MW, projected COD 09/20/2029
- 02/11/2026Screening → FIS Requested
Other projects at this substation