Piedra Solar is a 282 MW solar project in Freestone County, Texas, connecting at Tap 345-kV line Navarro (68091) – Limestone (46020)). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 01/15/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0168
- Capacity
- 282 MW
- Fuel
- Solar (PV)
- County
- Freestone County
- Interconnecting entity
- Piedra Solar, LLC
- Projected COD
- 01/15/2027
- Entered queue
- 09/02/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/26/2026Energization Approved → Sync Approved
- 07/27/2026IA Signed → Energization Approved
- 09/17/2025FIS Requested → FIS Approved
- 07/02/2024FIS Approved → IA Signed
- 03/07/2023Screening → FIS Requested
- 09/02/2022Entered the queue with 282 MW, projected COD 01/15/2027