Douie Solar

Douie Solar is a 221 MW solar project in Freestone County, Texas, connecting at Tap 138 kV 3501 Sea way Teague - 3394 Jewett. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/18/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0098
Capacity
221 MW
Fuel
Solar (PV)
Interconnecting entity
Buffalo Spring Solar LLC
Projected COD
04/18/2028
Entered queue
05/12/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/08/2026
    FIS Approved → IA Signed
  • 07/07/2025
    FIS Requested → FIS Approved
  • 05/12/2023
    Entered the queue with 221 MW, projected COD 04/18/2028
  • 05/12/2023
    Screening → FIS Requested

Other projects at this substation