LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0289 · Solar · Freestone County

Ratcliff Solar

Ratcliff Solar is a 86 MW solar project in Freestone County, Texas, connecting at Tap 138kV 3279 Long Lake Tap Switch - 3280 Long Lake. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/07/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0289
Capacity
86 MW
Fuel
Solar (PV)
Interconnecting entity
Greenalia Solar Power Ratcliff
Projected COD
04/07/2029
Entered queue
06/27/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/17/2022
    Screening → FIS Requested
  • 06/27/2022
    Entered the queue with 86 MW, projected COD 04/07/2029

Other projects at this substation

No other projects at this substation.