24INR0289 · Solar · Freestone County
Ratcliff Solar
Ratcliff Solar is a 86 MW solar project in Freestone County, Texas, connecting at Tap 138kV 3279 Long Lake Tap Switch - 3280 Long Lake. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/07/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0289
- Capacity
- 86 MW
- Fuel
- Solar (PV)
- County
- Freestone County
- Interconnecting entity
- Greenalia Solar Power Ratcliff
- Projected COD
- 04/07/2029
- Entered queue
- 06/27/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/17/2022Screening → FIS Requested
- 06/27/2022Entered the queue with 86 MW, projected COD 04/07/2029