Amerada Storage

Amerada Storage is a 151 MW battery storage project in Freestone County, Texas, connecting at Tap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/21/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0084
Capacity
151 MW
Fuel
BESS (BA)
Interconnecting entity
Amerada Solar, LLC
Projected COD
07/21/2028
Entered queue
04/28/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/28/2023
    Entered the queue with 151 MW, projected COD 07/21/2028
  • 04/28/2023
    Screening → FIS Requested

Other projects at this substation

Amerada SolarSolar302 MWFIS Requested