26INR0084 · BESS · Freestone County
Amerada Storage
Amerada Storage is a 151 MW battery storage project in Freestone County, Texas, connecting at Tap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/21/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0084
- Capacity
- 151 MW
- Fuel
- BESS (BA)
- County
- Freestone County
- Interconnecting entity
- Amerada Solar, LLC
- Projected COD
- 07/21/2028
- Entered queue
- 04/28/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/28/2023Entered the queue with 151 MW, projected COD 07/21/2028
- 04/28/2023Screening → FIS Requested
Other projects at this substation
| Amerada Solar | Solar | 302 MW | FIS Requested |