LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection · Freestone County

Long Lake Sub (Bus 3280) – Long Lake Tap Switch (Bus 3279)

2 active projects totalling 200 MW are queued to connect at Long Lake Sub (Bus 3280) – Long Lake Tap Switch (Bus 3279) in Freestone County, Texas, according to ERCOT's October 2026 report.

Active capacity
200 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0269Bar Candela Solar SLFSolar200IA Signed05/16/20291
24INR0271Bar Candela Storage SLFBESS0IA Signed05/16/20291