LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Texas grid · ERCOT interconnection queue

What changed in the Texas queue

In ERCOT's October 2026 report, 23 projects entered the Texas interconnection queue, 50 projects left it and 116 projects pushed back their commercial operation date. 1,789 projects totalling 438.8 GW are now waiting to connect.

New projects
+23
10.1 GW added
Withdrawn
−50
8.8 GW removed
COD delays
116
start date pushed back
Stage changes
74
moved to a later stage

October 2026 report by fuel

See all 299 changes

Number of projects with each kind of change. Click a row to see the projects.

ChangeBESSSolarWindGasOtherTotalSize
New projects31224223+10,066 MW
Withdrawals262022·50−8,814 MW
Stage changes19452717413 signed an IA
COD changes50458201124116 later · avg +11 mo
MW changes81064·28net −1,938 MW

Find your county

See every power project planned in a Texas county and what changed this month.

The queue today, by stage

Active projects by the furthest milestone ERCOT lists for them.

StageProjectsCapacityShare of active MW
Screening316.8 GW
FIS Requested1,028273.2 GW
FIS Approved10418.5 GW
IA Signed494119.7 GW
Energization Approved80.9 GW
Sync Approved12419.7 GW
All active1,789438.8 GW

Counties with the most queued capacity

  1. Pecos County57 active projects21,374 MW
  2. Brazoria County56 active projects11,487 MW
  3. Wharton County42 active projects8,625 MW
  4. Wilbarger County21 active projects8,506 MW
  5. Reeves County24 active projects8,350 MW
  6. Milam County29 active projects8,290 MW