27INR0652 · Gas · Freestone County
Three Canes Gas P2
Three Canes Gas P2 is a 0 MW natural gas project in Freestone County, Texas, connecting at Tap on the 345 kV Outlaw Switch (bus #3386) to Limestone Plant Station (bus #46020) Transmission Line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/30/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0652
- Capacity
- 0 MW
- Fuel
- Gas (IC)
- County
- Freestone County
- Interconnecting entity
- CleanAI, LLC
- Projected COD
- 11/30/2027
- Entered queue
- 06/26/2026
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/26/2026Entered the queue with 0 MW, projected COD 11/30/2027
- 06/26/2026Screening → FIS Requested
Other projects at this substation