Substation / point of interconnection · Freestone County
Tap 345-kV line Navarro (68091) – Limestone (46020))
2 active projects totalling 385 MW are queued to connect at Tap 345-kV line Navarro (68091) – Limestone (46020)) in Freestone County, Texas, according to ERCOT's October 2026 report.
Active capacity
385 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0168 | Piedra Solar | Solar | 282 | Sync Approved | 01/15/2027 | 0 |
| 25INR0169 | Piedra BESS | BESS | 104 | IA Signed | 12/01/2027 | 0 |