28INR0080 · BESS · Freestone County
Turtle Rock Storage
Turtle Rock Storage is a 136 MW battery storage project in Freestone County, Texas, connecting at Tap 138 kV 13501 Clayhill to 13681 Reed. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/02/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0080
- Capacity
- 136 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138 kV 13501 Clayhill to 13681 Reed
- County
- Freestone County
- Interconnecting entity
- Turtle Rock Energy Center, LLC
- Projected COD
- 07/02/2028
- Entered queue
- 05/08/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/08/2024Entered the queue with 136 MW, projected COD 07/02/2028
- 05/08/2024Screening → FIS Requested
Other projects at this substation