ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0269 · Solar · Freestone County

Bar Candela Solar SLF

COD delayed 1×

Bar Candela Solar SLF is a 200 MW solar project in Freestone County, Texas, connecting at Long Lake Sub (Bus 3280) – Long Lake Tap Switch (Bus 3279). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/16/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0269
Capacity
200 MW
Fuel
Solar (PV)
Interconnecting entity
Bar Candela Solar Project LLC
Projected COD
05/16/2029
Entered queue
03/21/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/31/2027 → 05/16/2029 (+17 months)
  • 05/06/2025
    FIS Requested → IA Signed
  • 12/06/2022
    Screening → FIS Requested
  • 03/21/2022
    Entered the queue with 200 MW, projected COD 12/31/2027

Other projects at this substation

Bar Candela Storage SLFBESS0 MWIA Signed