ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0033 · BESS · Freestone County

Fairway Storage

Fairway Storage is a 120 MW battery storage project in Freestone County, Texas, connecting at Tap 138kV 3503 FAIRWPOD_8 - 196 FAIRFIELD. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/24/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0033
Capacity
120 MW
Fuel
BESS (BA)
Interconnecting entity
Fairway Storage LLC
Projected COD
09/24/2027
Entered queue
11/07/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/11/2025
    FIS Requested → IA Signed
  • 02/15/2023
    Screening → FIS Requested
  • 11/07/2022
    Entered the queue with 120 MW, projected COD 09/24/2027

Other projects at this substation

No other projects at this substation.