25INR0169 · BESS · Freestone County
Piedra BESS
Piedra BESS is a 104 MW battery storage project in Freestone County, Texas, connecting at Tap 345-kV line Navarro (68091) – Limestone (46020)). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0169
- Capacity
- 104 MW
- Fuel
- BESS (BA)
- County
- Freestone County
- Interconnecting entity
- Piedra Solar, LLC
- Projected COD
- 12/01/2027
- Entered queue
- 09/02/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/18/2025FIS Requested → FIS Approved
- 07/02/2024FIS Approved → IA Signed
- 03/07/2023Screening → FIS Requested
- 09/02/2022Entered the queue with 104 MW, projected COD 12/01/2027
Other projects at this substation
| Piedra Solar | Solar | 282 MW | Sync Approved |