Ellis County power projects
Ellis County, Texas has 27 active power projects totalling 5,887 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 3,278 MW (56%). The largest single project is Kickstart Energy Storage VI (1,026 MW battery storage). 4 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
27
5.9 GW capacity
IA signed or later
4
15% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
7
since Sep 2026
Changes in Ellis County
New
10/01/2026
Old Alma Road Solar · Solar · Ellis County
Entered the queue at 2326 ENNS_SE_8 138kV. Projected COD 10/31/2028.
+20 MW
COD change
10/01/2026
Digital Ranch Gas · Gas · Ellis County
Projected COD moved 12/01/2027 → 04/15/2030. Delay #1 for this project.
+28 mo
COD change
10/01/2026
Midlothian Unit 2 repower · Gas · Ellis County
Projected COD moved 06/03/2027 → 06/03/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Midlothian 4 repower · Gas · Ellis County
Projected COD moved 06/03/2027 → 06/03/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Midlothian Unit 3 repower · Gas · Ellis County
Projected COD moved 06/03/2027 → 06/03/2028. Delay #1 for this project.
+12 mo
Stage change
09/17/2026
FIS Approved
Stage change
09/02/2026
Energization Approved
All projects
For residents and landowners
- What power projects are planned in Ellis County?
- ERCOT's October 2026 report lists 27 active projects in Ellis County totalling 5,887 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.