Substation / point of interconnection ยท Ellis County

345 KV Venus 1906 to Fort Smith 3389

1 active project totalling 999 MW is queued to connect at 345 KV Venus 1906 to Fort Smith 3389 in Ellis County, Texas, according to ERCOT's October 2026 report.

Active capacity
999 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0217Kickstart Energy Storage VBESS999FIS Requested12/31/20290