22INR0543 · Gas · Ellis County

Midlothian Unit 3 repower

COD delayed 1×

Midlothian Unit 3 repower is a 18 MW natural gas project in Ellis County, Texas, connecting at 1940 Midlothian ELP 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/03/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0543
Capacity
18 MW
Fuel
Gas (GT)
Interconnecting entity
MIDLOTHIAN ENERGY, LLC
Projected COD
06/03/2028
Entered queue
05/11/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 06/03/2027 → 06/03/2028 (+12 months)
  • 05/11/2021
    Entered the queue with 18 MW, projected COD 06/03/2027
  • 05/11/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.