Galaxy Storage
Galaxy Storage is a 155 MW battery storage project in Ellis County, Texas, connecting at Stainback Switch (bus #2217) - Elrod Switch (bus #3159). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0220
- Capacity
- 155 MW
- Fuel
- BESS (BA)
- County
- Ellis County
- Interconnecting entity
- Galaxy Solar, LLC
- Projected COD
- 10/30/2028
- Entered queue
- 03/22/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/16/2024Screening → FIS Requested
- 03/22/2024Entered the queue with 155 MW, projected COD 10/30/2028