27INR0472 · BESS · Ellis County
Kickstart Energy Storage IV
Kickstart Energy Storage IV is a 1.4 MW battery storage project in Ellis County, Texas, connecting at Tap 345 kV #1906 VENUS_S5 to #68091 NAVARRO. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0472
- Capacity
- 1.4 MW
- Fuel
- BESS (BA)
- County
- Ellis County
- Interconnecting entity
- Kickstart Infrastructure LLC
- Projected COD
- 09/30/2029
- Entered queue
- 03/10/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/10/2025Entered the queue with 1.4 MW, projected COD 09/30/2029
- 03/10/2025Screening → FIS Requested
Other projects at this substation
| Kickstart Energy Storage III | BESS | 1 MW | FIS Requested |