ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
21INR0534 · Gas · Ellis County

Midlothian Unit 2 repower

COD delayed 1×

Midlothian Unit 2 repower is a 18 MW natural gas project in Ellis County, Texas, connecting at 1939 Midlothian ELP 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/03/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0534
Capacity
18 MW
Fuel
Gas (GT)
Interconnecting entity
MIDLOTHIAN ENERGY, LLC
Projected COD
06/03/2028
Entered queue
01/25/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 06/03/2027 → 06/03/2028 (+12 months)
  • 02/08/2021
    Screening → FIS Requested
  • 01/25/2021
    Entered the queue with 18 MW, projected COD 06/03/2027

Other projects at this substation

No other projects at this substation.