ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0495 · BESS · Ellis County

Dolomite Storage

Dolomite Storage is a 126 MW battery storage project in Ellis County, Texas, connecting at 218 Rockett 69kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0495
Capacity
126 MW
Fuel
BESS (BA)
Interconnecting entity
BT Wilson Storage, LLC
Projected COD
12/01/2026
Entered queue
08/22/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/22/2023
    Entered the queue with 126 MW, projected COD 12/01/2026
  • 08/22/2023
    Screening → FIS Requested