LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0471 · BESS · Ellis County

Kickstart Energy Storage III

Kickstart Energy Storage III is a 1.4 MW battery storage project in Ellis County, Texas, connecting at Tap 345 kV #1906 VENUS_S5 to #68091 NAVARRO. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0471
Capacity
1.4 MW
Fuel
BESS (BA)
Interconnecting entity
Kickstart Infrastructure LLC
Projected COD
09/30/2029
Entered queue
03/10/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/10/2025
    Entered the queue with 1.4 MW, projected COD 09/30/2029
  • 03/10/2025
    Screening → FIS Requested

Other projects at this substation

Kickstart Energy Storage IVBESS1 MWFIS Requested