29INR0218 · BESS · Ellis County
Kickstart Energy Storage VI
Kickstart Energy Storage VI is a 1,026 MW battery storage project in Ellis County, Texas, connecting at 345 KV Venus 1907 to Navarro 68091. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0218
- Capacity
- 1,026 MW
- Fuel
- BESS (BA)
- Substation
- 345 KV Venus 1907 to Navarro 68091
- County
- Ellis County
- Interconnecting entity
- Kickstart Infrastructure LLC
- Projected COD
- 12/31/2029
- Entered queue
- 11/21/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/21/2025Entered the queue with 1,026 MW, projected COD 12/31/2029
- 11/21/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.