Substation / point of interconnection ยท Ellis County
#1906 Venus Switch 345 kV
1 active project totalling 378 MW is queued to connect at #1906 Venus Switch 345 kV in Ellis County, Texas, according to ERCOT's October 2026 report.
Active capacity
378 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0100 | Digital Ranch Gas | Gas | 378 | FIS Requested | 04/15/2030 | 1 |