Hopkins County power projects

Hopkins County, Texas has 13 active power projects totalling 2,219 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,281 MW (58%). The largest single project is Dairyland Storage (302 MW battery storage). 5 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
13
2.2 GW capacity
IA signed or later
5
38% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Hopkins County

COD change
10/01/2026
Pine Forest Solar · Solar · Hopkins County
Projected COD moved 10/01/2026 → 02/01/2027. Delay #1 for this project.
+4 mo
Stage change
09/17/2026
Cedar Range Solar · Solar · Hopkins County
Moved from FIS Requested to FIS Approved.
FIS Approved
Stage change
09/17/2026
Blarney Solar · Solar · Hopkins County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

For residents and landowners

What power projects are planned in Hopkins County?
ERCOT's October 2026 report lists 13 active projects in Hopkins County totalling 2,219 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.