Substation / point of interconnection · Hopkins County
“Sweet Tea” 345 kV switchyard that taps the Allen Switch – Stouts Creek 345 kV Line
1 active project totalling 151 MW is queued to connect at “Sweet Tea” 345 kV switchyard that taps the Allen Switch – Stouts Creek 345 kV Line in Hopkins County, Texas, according to ERCOT's October 2026 report.
Active capacity
151 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0204 | Cedar Range Solar | Solar | 151 | IA Signed | 09/17/2027 | 0 |