ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0204 · Solar · Hopkins County

Cedar Range Solar

Cedar Range Solar is a 151 MW solar project in Hopkins County, Texas, connecting at “Sweet Tea” 345 kV switchyard that taps the Allen Switch – Stouts Creek 345 kV Line. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/17/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0204
Capacity
151 MW
Fuel
Solar (PV)
Interconnecting entity
Cedar Range, LLC
Projected COD
09/17/2027
Entered queue
09/21/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/17/2026
    FIS Requested → FIS Approved
  • 07/02/2025
    FIS Approved → IA Signed
  • 11/03/2022
    Screening → FIS Requested
  • 09/21/2022
    Entered the queue with 151 MW, projected COD 09/17/2027

Other projects at this substation

No other projects at this substation.