26INR0304 · Solar · Hopkins County
JUNIPERUSSS
JUNIPERUSSS is a 80 MW solar project in Hopkins County, Texas, connecting at Tap 345kV Cash Switch (bus# 2464) - Sandy Ranch Switch (bus# 2621). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/09/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0304
- Capacity
- 80 MW
- Fuel
- Solar (PV)
- County
- Hopkins County
- Interconnecting entity
- BLUE STONE RENEWABLE XXI LLC
- Projected COD
- 07/09/2029
- Entered queue
- 01/04/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/04/2024Entered the queue with 80 MW, projected COD 07/09/2029
- 01/04/2024Screening → FIS Requested
Other projects at this substation
| JUNIPERUS BESS | BESS | 170 MW | FIS Requested |