Substation / point of interconnection · Hopkins County
Monticello Switch – Allen Switch 345 kV Line
1 active project totalling 302 MW is queued to connect at Monticello Switch – Allen Switch 345 kV Line in Hopkins County, Texas, according to ERCOT's October 2026 report.
Active capacity
302 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 20INR0203 | Pine Forest Solar | Solar | 302 | Sync Approved | 02/01/2027 | 1 |