29INR0056 · Solar · Hopkins County

Palomino Solar

Palomino Solar is a 301 MW solar project in Hopkins County, Texas, connecting at Tap 345kV 1695 Monticello - 1697 Sulphur Springs. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0056
Capacity
301 MW
Fuel
Solar (PV)
Interconnecting entity
Palomino Renewables
Projected COD
12/31/2028
Entered queue
10/18/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/09/2025
    Screening → FIS Requested
  • 10/18/2024
    Entered the queue with 301 MW, projected COD 12/31/2028

Other projects at this substation

Palomino StorageBESS155 MWFIS Requested