23INR0495 · BESS · Hopkins County

Cartwheel BESS 2

Cartwheel BESS 2 is a 157 MW battery storage project in Hopkins County, Texas, connecting at Tap 345kV 1697 Sulphur Springs Switch – 2464 Cash Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0495
Capacity
157 MW
Fuel
BESS (BA)
Interconnecting entity
RWE Renewables
Projected COD
06/15/2028
Entered queue
05/10/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/10/2022
    Entered the queue with 157 MW, projected COD 06/15/2028
  • 05/10/2022
    Screening → FIS Requested

Other projects at this substation

Cartwheel BESS 1BESS154 MWSync Approved