20INR0203 · Solar · Hopkins County

Pine Forest Solar

COD delayed 1×

Pine Forest Solar is a 302 MW solar project in Hopkins County, Texas, connecting at Monticello Switch – Allen Switch 345 kV Line. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 02/01/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0203
Capacity
302 MW
Fuel
Solar (PV)
Interconnecting entity
Pine Forest Solar I, LLC
Projected COD
02/01/2027
Entered queue
10/04/2018
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/01/2026 → 02/01/2027 (+4 months)
  • 07/03/2025
    Energization Approved → Sync Approved
  • 06/03/2025
    IA Signed → Energization Approved
  • 12/18/2024
    Screening → FIS Approved
  • 07/29/2020
    FIS Approved → IA Signed
  • 10/04/2018
    Entered the queue with 302 MW, projected COD 10/01/2026