27INR0451 · BESS · Hopkins County

Dairyland Storage

Dairyland Storage is a 302 MW battery storage project in Hopkins County, Texas, connecting at To 345 kV Birthright Station (#11684). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/30/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0451
Capacity
302 MW
Fuel
BESS (BA)
Interconnecting entity
ENGIE IR Holdings LLC
Projected COD
04/30/2029
Entered queue
02/04/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/04/2025
    Entered the queue with 302 MW, projected COD 04/30/2029
  • 02/04/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.