Cartwheel BESS 1

Cartwheel BESS 1 is a 154 MW battery storage project in Hopkins County, Texas, connecting at Tap 345kV 1697 Sulphur Springs Switch – 2464 Cash Switch. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0494
Capacity
154 MW
Fuel
BESS (BA)
Interconnecting entity
Cartwheel BESS, LLC
Projected COD
12/31/2026
Entered queue
05/10/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/10/2025
    Energization Approved → Sync Approved
  • 06/26/2025
    IA Signed → Energization Approved
  • 04/12/2024
    FIS Requested → FIS Approved
  • 11/10/2023
    FIS Approved → IA Signed
  • 05/10/2022
    Entered the queue with 154 MW, projected COD 12/31/2026
  • 05/10/2022
    Screening → FIS Requested

Other projects at this substation

Cartwheel BESS 2BESS157 MWFIS Requested