LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Mitchell County power projects

Mitchell County, Texas has 15 active power projects totalling 6,791 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 3,824 MW (56%). The largest single project is Zeus Mitchell BESS (1,043 MW battery storage). 1 project has signed an interconnection agreement or reached a later stage. 4 projects in the county are listed as withdrawn or cancelled.

Active projects
15
6.8 GW capacity
IA signed or later
1
7% of active projects
Withdrawn or cancelled
4
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Mitchell County

COD change
10/01/2026
Rosenix Solar · Solar · Mitchell County
Projected COD moved 12/31/2029 → 04/20/2030. Delay #1 for this project.
+4 mo
COD change
10/01/2026
Rosenix Storage · BESS · Mitchell County
Projected COD moved 12/31/2029 → 04/20/2030. Delay #1 for this project.
+4 mo
MW change
10/01/2026
Rosenix Solar · Solar · Mitchell County
Requested capacity reduced.
510 → 502 MW
MW change
10/01/2026
Rosenix Storage · BESS · Mitchell County
Requested capacity increased.
250 → 258 MW

All projects

ProjectFuelMWSubstationStageCOD
Zeus Mitchell BESSBESS1,043Tap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02FIS Requested04/17/2029
Zeus Mitchell BESS IIBESS1,043Tap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02FIS Requested05/01/2027
Zeus Spade WindWind987Tap 345 kV 1030 Morgan Creek to 76030 Gasconades CreekFIS Requested03/20/2028
Zeus Mitchell SolarSolar805Tap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02FIS Requested04/17/2029
Rosenix SolarSolar502Cattleman (#10053) – Gasconades (#76030)FIS Requested04/20/2030
Zeus Spade BESSBESS446Tap 345 kV 1030 Morgan Creek to 76030 Gasconades CreekFIS Requested03/20/2028
Rabbit Hollow Energy StorageBESS3421190 Barber Lake Switch 138kVFIS Requested12/31/2029
Prairie Power WindWind303Tap 345 kV Longshore Switch (Bus# 1058) to Cattleman Switch (Bus# 10053) CKT 4FIS Requested04/17/2029
Rosenix StorageBESS258Cattleman (#10053) – Gasconades (#76030)FIS Requested04/20/2030
Sunflower Valley StorageBESS2061414 Champion Creek Substation 345 kVFIS Requested04/17/2029
Sepik BESSBESS205tap 138kV 11342 Loraine South – 10050 Ranger CampFIS Requested03/01/2028
Johnson Grass SolarSolar196Tap 138kV (#11395) Navigation - (#10054) CattlemenFIS Requested04/19/2028
Whitetail BESSBESS180tap Salt Mine (#23846) to Bulldog (#23833) 138kVFIS Requested06/08/2029
Hackberry Creek SolarSolar176tap 345kV 10053 Cattleman Switch - 1058 Longshore SwitchIA Signed01/01/2028
Dolce BESSBESS101Tap 138kV 1189 BARBER_LK1_8 - 19520 CHINAGRVX2_8FIS Approved01/31/2029
River Boat SolarSolar502Not listedWithdrawnn/a
River Boat Power Gas PlantGas334Not listedWithdrawnn/a
River Boat StorageBESS207Not listedWithdrawnn/a
Jayhawk SolarSolar102Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Mitchell County?
ERCOT's October 2026 report lists 15 active projects in Mitchell County totalling 6,791 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.