Rosenix Solar

COD delayed 1×

Rosenix Solar is a 502 MW solar project in Mitchell County, Texas, connecting at Cattleman (#10053) – Gasconades (#76030). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/20/2030. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0212
Capacity
502 MW
Fuel
Solar (PV)
Interconnecting entity
Rosenix Solar, LLC
Projected COD
04/20/2030
Entered queue
07/01/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/31/2029 → 04/20/2030 (+4 months)
  • 10/01/2026
    Capacity 510 → 502 MW
  • 07/01/2026
    Entered the queue with 510 MW, projected COD 12/31/2029
  • 07/01/2026
    Screening → FIS Requested