23INR0143 · BESS · Mitchell County
Sepik BESS
Sepik BESS is a 205 MW battery storage project in Mitchell County, Texas, connecting at tap 138kV 11342 Loraine South – 10050 Ranger Camp. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0143
- Capacity
- 205 MW
- Fuel
- BESS (BA)
- County
- Mitchell County
- Interconnecting entity
- BRP Sepik BESS LLC
- Projected COD
- 03/01/2028
- Entered queue
- 12/01/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/01/2020Entered the queue with 205 MW, projected COD 03/01/2028
- 12/01/2020Screening → FIS Requested
Other projects at this substation