29INR0213 · BESS · Mitchell County
Rosenix Storage
COD delayed 1×
Rosenix Storage is a 258 MW battery storage project in Mitchell County, Texas, connecting at Cattleman (#10053) – Gasconades (#76030). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/20/2030. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0213
- Capacity
- 258 MW
- Fuel
- BESS (BA)
- Substation
- Cattleman (#10053) – Gasconades (#76030)
- County
- Mitchell County
- Interconnecting entity
- Rosenix Solar, LLC
- Projected COD
- 04/20/2030
- Entered queue
- 07/10/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 12/31/2029 → 04/20/2030 (+4 months)
- 10/01/2026Capacity 250 → 258 MW
- 07/10/2026Entered the queue with 250 MW, projected COD 12/31/2029
- 07/10/2026Screening → FIS Requested
Other projects at this substation
| Rosenix Solar | Solar | 502 MW | FIS Requested |