Substation / point of interconnection ยท Mitchell County
tap 345kV 10053 Cattleman Switch - 1058 Longshore Switch
1 active project totalling 176 MW is queued to connect at tap 345kV 10053 Cattleman Switch - 1058 Longshore Switch in Mitchell County, Texas, according to ERCOT's October 2026 report.
Active capacity
176 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0430 | Hackberry Creek Solar | Solar | 176 | IA Signed | 01/01/2028 | 0 |