26INR0386 · Wind · Mitchell County

Zeus Spade Wind

Zeus Spade Wind is a 987 MW wind project in Mitchell County, Texas, connecting at Tap 345 kV 1030 Morgan Creek to 76030 Gasconades Creek. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/20/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0386
Capacity
987 MW
Fuel
Wind (WT)
Interconnecting entity
Spade Wind, LLC
Projected COD
03/20/2028
Entered queue
03/29/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/07/2025
    Screening → FIS Requested
  • 03/29/2024
    Entered the queue with 987 MW, projected COD 03/20/2028

Other projects at this substation

Zeus Spade BESSBESS446 MWFIS Requested