27INR0327 · BESS · Mitchell County
Sunflower Valley Storage
Sunflower Valley Storage is a 206 MW battery storage project in Mitchell County, Texas, connecting at 1414 Champion Creek Substation 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/17/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0327
- Capacity
- 206 MW
- Fuel
- BESS (BA)
- Substation
- 1414 Champion Creek Substation 345 kV
- County
- Mitchell County
- Interconnecting entity
- Sunflower Valley Storage, LLC
- Projected COD
- 04/17/2029
- Entered queue
- 04/08/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/08/2025Entered the queue with 206 MW, projected COD 04/17/2029
- 04/08/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.