ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0307 · Wind · Mitchell County

Prairie Power Wind

Prairie Power Wind is a 303 MW wind project in Mitchell County, Texas, connecting at Tap 345 kV Longshore Switch (Bus# 1058) to Cattleman Switch (Bus# 10053) CKT 4. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/17/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0307
Capacity
303 MW
Fuel
Wind (WT)
Interconnecting entity
Prairie Power Wind, LLC
Projected COD
04/17/2029
Entered queue
05/27/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/27/2025
    Entered the queue with 303 MW, projected COD 04/17/2029
  • 05/27/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.