28INR0119 · BESS · Mitchell County
Rabbit Hollow Energy Storage
Rabbit Hollow Energy Storage is a 342 MW battery storage project in Mitchell County, Texas, connecting at 1190 Barber Lake Switch 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0119
- Capacity
- 342 MW
- Fuel
- BESS (BA)
- Substation
- 1190 Barber Lake Switch 138kV
- County
- Mitchell County
- Interconnecting entity
- Rabbit Hollow Energy Storage, LLC
- Projected COD
- 12/31/2029
- Entered queue
- 12/01/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/01/2024Entered the queue with 342 MW, projected COD 12/31/2029
- 12/01/2024Screening → FIS Requested