LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Jack County power projects

Jack County, Texas has 17 active power projects totalling 7,978 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 2,638 MW (33%). The largest single project is Thunder Bird 2 Gas (1,273 MW natural gas). 4 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
17
8.0 GW capacity
IA signed or later
4
24% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Jack County

COD change
10/01/2026
Possum Kingdom Solar · Solar · Jack County
Projected COD moved 10/29/2027 → 06/21/2028. Delay #1 for this project.
+8 mo
COD change
10/01/2026
Possum Kingdom BESS · BESS · Jack County
Projected COD moved 10/29/2027 → 10/29/2028. Delay #1 for this project.
+12 mo
MW change
10/01/2026
Thunder Bird 2 Gas · Gas · Jack County
Requested capacity reduced.
1,274 → 1,273 MW

All projects

ProjectFuelMWSubstationStageCOD
Thunder Bird 2 GasGas1,273Tap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (1421) and Jacksbro_5 (1429) to Hendrch_5 (1443)FIS Requested06/14/2031
Thunder Bird 1 GasGas1,273Tap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (1421) and Jacksbro_5 (1429) to Hendrch_5 (1443)FIS Requested06/14/2030
Dovetail Solar 1Solar666Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing Ckt 2FIS Requested04/12/2028
Dovetail Solar 2Solar666Tap 345 KV 1421 Willow Creek - 60515 Clear CrossingFIS Requested04/20/2029
Dovetail Solar 3Solar666Tap 345kV 1421 Willow Creek – 11523 THOMPRICFIS Requested04/20/2029
Dovetail StorageBESS509Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing Ckt 2FIS Requested04/12/2028
Pinnington StorageBESS503tap both 345kV 1430 Graham - 1436 Parker 345kV linesFIS Requested04/20/2029
O'Bannion Energy StorageBESS3061506 Long Hollow Switch 345 kVIA Signed04/21/2028
Wooderson Energy StorageBESS306Tap 345 kV 11418 TECUMSEH- 1421 Willow CreekFIS Requested09/30/2028
Fortuna WindWind295Tap 345kV 1429 Jacksboro - 1730 WKrumIA Signed07/01/2026
Possum Kingdom SolarSolar262Tap 345kV 1421 Willow Creek Switch – 11523 Thomas PriceIA Signed06/21/2028
Campsey WindWind238tap 345kV 1458 Cobb - 1429 JacksboroFIS Approved06/01/2028
Liberty Senate Energy Storage 1BESS2071445 Burwick 345kVFIS Requested10/27/2027
Lightning Ridge Energy StorageBESS205Tap #1429 Jacksboro Substation 345kVFIS Approved03/21/2028
Possum Kingdom BESSBESS201Tap 345kV 1421 Willow Creek – 11523 Thomas PriceIA Signed10/29/2028
Beitel Energy StorageBESS201579 Jack County 138kVFIS Requested12/31/2027
JackGard BESSBESS2011429 Jacksboro 345kVFIS Approved04/17/2028

For residents and landowners

What power projects are planned in Jack County?
ERCOT's October 2026 report lists 17 active projects in Jack County totalling 7,978 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.