LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Jack County

579 Jack County 138kV

1 active project totalling 201 MW is queued to connect at 579 Jack County 138kV in Jack County, Texas, according to ERCOT's October 2026 report.

Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0185Beitel Energy StorageBESS201FIS Requested12/31/20270