26INR0185 · BESS · Jack County

Beitel Energy Storage

Beitel Energy Storage is a 201 MW battery storage project in Jack County, Texas, connecting at 579 Jack County 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0185
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Brazos Energy Storage, LLC
Projected COD
12/31/2027
Entered queue
08/02/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/02/2023
    Entered the queue with 201 MW, projected COD 12/31/2027
  • 08/02/2023
    Screening → FIS Requested