Substation / point of interconnection ยท Jack County
1445 Burwick 345kV
1 active project totalling 207 MW is queued to connect at 1445 Burwick 345kV in Jack County, Texas, according to ERCOT's October 2026 report.
Active capacity
207 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0334 | Liberty Senate Energy Storage 1 | BESS | 207 | FIS Requested | 10/27/2027 | 0 |