Substation / point of interconnection ยท Jack County
Tap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (1421) and Jacksbro_5 (1429) to Hendrch_5 (1443)
2 active projects totalling 2,546 MW are queued to connect at Tap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (1421) and Jacksbro_5 (1429) to Hendrch_5 (1443) in Jack County, Texas, according to ERCOT's October 2026 report.
Active capacity
2,546 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0509 | Thunder Bird 2 Gas | Gas | 1,273 | FIS Requested | 06/14/2031 | 0 |
| 30INR0110 | Thunder Bird 1 Gas | Gas | 1,273 | FIS Requested | 06/14/2030 | 0 |