26INR0460 · BESS · Jack County

Lightning Ridge Energy Storage

Lightning Ridge Energy Storage is a 205 MW battery storage project in Jack County, Texas, connecting at Tap #1429 Jacksboro Substation 345kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 03/21/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0460
Capacity
205 MW
Fuel
BESS (BA)
Interconnecting entity
Lightning Ridge Storage LLC
Projected COD
03/21/2028
Entered queue
03/27/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/24/2025
    FIS Requested → FIS Approved
  • 03/27/2024
    Entered the queue with 205 MW, projected COD 03/21/2028
  • 03/27/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.