22INR0301 · Wind · Jack County
Fortuna Wind
COD date passed
Fortuna Wind is a 295 MW wind project in Jack County, Texas, connecting at Tap 345kV 1429 Jacksboro - 1730 WKrum. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2026. Its projected COD of 07/01/2026 has already passed without ERCOT approval to synchronize, so the date is likely to move.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0301
- Capacity
- 295 MW
- Fuel
- Wind (WT)
- Substation
- Tap 345kV 1429 Jacksboro - 1730 WKrum
- County
- Jack County
- Interconnecting entity
- RWE Renewables Development, LLC
- Projected COD
- 07/01/2026
- Entered queue
- 03/06/2020
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/08/2024FIS Approved → IA Signed
- 05/09/2024FIS Requested → FIS Approved
- 11/24/2020Screening → FIS Requested
- 03/06/2020Entered the queue with 295 MW, projected COD 07/01/2026
Other projects at this substation
No other projects at this substation.